Hartley Landfill Cell B

Hartley Landfill Cell B

Buttrose Earthmovers was engaged to construct a new landfill cell as part of the expansion a large landfill facility in Hartley.

Hartley Landfill Cell B

ProjectHartley Landfill Cell B
Duration10 Months
LocationHartley, SA
Sector
Services

This facility is used for the disposal of commercial and industrial waste, domestic waste, inert waste, municipal solid waste and intermediate waste.

SCOPE OF WORKS

  • Construction of a new landfill cell
  • Rock blasting, completed inhouse
  • Rock breaking & ripping
  • Excavation of approximately 55,000m3 of soil & rock
  • Construction of clay bunds
  • Installation of geosynthetic liners
  • Installation of a leachate collection system
  • Placement of sidewall protection layers
  • Workforce peaked at 10 personnel achieving 6,275 hours
  • Utilising equipment including excavators up to 50T, 14M grader, D8T dozer, articulated dump trucks, moxy water truck & rollers