ProjectMinda Dunes Rock Wall
Duration8 Weeks
LocationSomerton Park, SA
Sector
Services
SCOPE OF WORKS
Bulk and civil works as follows;
- Vegetation removal
- Dismantling existing 200m rock wall
- Preparing subgrade for new rock wall
- Rock testing & rock sorting
- Placement of geotextile
- Placement of filter layer
- Placement of primary armour layer
- Placement of toe rocks
- Reinstatement of beach