Wallaroo Bunker Stg 3
ProjectWallaroo Bunker Stg 3
Duration5 Months
LocationWallaroo, SA
Sector
Services
During the 2022 harvest the site was filled to its capacity. With servicing the YP growers as the highest priority, stage 3 of the project was engaged during June 2023 for the site to completed by harvest of 2023.
SCOPE OF WORKS
- Vegetation clearing
- Topsoil Stripping over 400,000m2
- Cut to fill to 70,000m3
- Conditioning of 120,000 tonnes of site crushed/screened material
- Pavement construction
- Installation of stormwater crossing & headwalls
- Minor traffic control